Major boost as contracts are signed to complete €31m road crossing Clare/Limerick border


Coonagh to Knockalisheen distributor road set to fully open to traffic within two years
Construction of the long-awaited Coonagh to Knockalisheen Road, which crosses the Clare/Limerick border is set to get under way in the coming weeks.
It comes after Limerick City and County Council and Wills Brothers Ltd exchanged contracts on the building of the link road which will provide the estate of Moyross, on the northside of Limerick city, with a second entrance and exit.
The works will include the construction of a new 2.1km urban dual carriageway, major improvements to existing roads, and the development of pedestrian and cyclist facilities.
Construction of the road stopped suddenly in early 2022 after the collapse of the previous contractor Roadbridge. It meant the local authority had to retender for another firm to complete the project, sparking a delay of almost three years.
The road project also involves associated works such as the diversion of live services, new sewer systems, and landscaping.
It will be delivered in phases, with the dual carriageway between Coonagh and Knockalisheen scheduled to open after the first 12 months. The entire project is expected to be completed in just two years.


Dr Pat Daly, director general of Limerick City and County Council, said: "The Coonagh to Knockalisheen Distributor Road Scheme is crucial for improving connectivity and supporting future economic development. This infrastructure will facilitate greater access to essential services, employment, and educational facilities, making a significant difference in the lives of the people in Moyross and surrounding areas."
Limerick City and County Council said it is grateful for the support of the Department of Transport, the appointed consultants MRG and Roughan O’Donovan, and the community for their continued patience and cooperation.