WORKS have begun on the northbound carriageway from August bank holiday, Monday 7 after the southbound carriageway have been completed.

See below the coming week’s schedule and please be aware of possible traffic disruption or delays as a result.

Week starting Tuesday, August 8:

  • Wednesday, 9  – N18 Southbound – C2 to C1 Contraflow – Works to provide Loops at Gantry Mounted VMS close to J4.
  • Thursday, 10  – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Advance Milling
  • Friday, 11 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Advance Milling 

Week starting Monday, August 14:

  • Monday, 14  – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs
  • Tuesday, 15 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs
  • Wednesday,16 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs
  • Thursday, 17  – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs
  • Friday, 18  – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs

All works will be carried out under either a southbound or northbound road closure, with two way traffic maintained on a contraflow on the opposite carriageway.