Clare N18 roadworks updated schedule


WORKS have begun on the northbound carriageway from August bank holiday, Monday 7 after the southbound carriageway have been completed.
See below the coming week’s schedule and please be aware of possible traffic disruption or delays as a result.
Week starting Tuesday, August 8:
- Wednesday, 9 – N18 Southbound – C2 to C1 Contraflow – Works to provide Loops at Gantry Mounted VMS close to J4.
- Thursday, 10 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Advance Milling
- Friday, 11 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Advance Milling
Week starting Monday, August 14:
- Monday, 14 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs
- Tuesday, 15 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs
- Wednesday,16 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs
- Thursday, 17 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs
- Friday, 18 – N18 Northbound – C1 to C3 Contraflow – N18 Northbound Surfacing/Lining/Studs
All works will be carried out under either a southbound or northbound road closure, with two way traffic maintained on a contraflow on the opposite carriageway.